Home | FAQ | Questions? Call us at
512-270-5000

Construction Alerts

Current

  • Crews are digging out the southbound Express Lane underpass exit to downtown Austin. Crews will be working 24 hours a day to install steel piling and remove rock between the southbound mainlines and the temporary Cesar Chavez/5th Street southbound exit ramp. This work is expected to last for at least 4 months. Nighty left hand lane closures on the Cesar Chavez/5th Street exit ramp will be necessary to allow trucks hauling excavated material to safely leave the work site.
  • Crews are forming and pouring section of sidewalk along the northbound MoPac frontage road north of US 183. Expect nightly lane closures on the frontage road in that area.
  • Crews are preparing to pour the concrete bridge decks in early September.

  • Crews are installing bridge forms and steel in preparation for installation of the concrete bridge decks in late September or early October.

  • Crews are demolishing portions of the existing bridge deck and will be working to retrofit a couple of existing bridge bent caps in the next few weeks. They plan to pour the bridge decks in October.
    Left hand lane closures may be necessary after 5pm on Sunday July 13th and after 9pm Monday night July 14 through Thursday night July 17th. The lanes will reopen each morning by 5am. - See more at: http://www.mopacexpress.com/#sthash.pD1DKXW8.dpuf
    Left hand lane closures may be necessary after 5pm on Sunday July 13th and after 9pm Monday night July 14 through Thursday night July 17th. The lanes will reopen each morning by 5am. - See more at: http://www.mopacexpress.com/#sthash.pD1DKXW8.dpuf
  • Crews are finishing work on a retaining wall adjacent to the future Cesar Chavez/6th Street on ramp to northbound MoPac.
  • Crews are finalizing the installation and grading of roadway base material in preparation for paving the area between Anderson Lane and US 183
  • Crews are working on drainage, roadway grading and retaining walls as part of the collector distributor road that is being built under Steck on the northbound side of MoPac.

  • Crews are working on the approaches to the widened bridge and will be installing the bridge beams on Tuesday evening September 1st and Wednesday evening Seotember 2nd. Windsor Road will be closed at MoPac during those nights after 9pm while the beams are being installed.
  • Crews are working on the approaches to the widened bridge and will be installing the southbound bridge beams on Monday August 31st with a complete closure of Westover Road at MoPac on Monday evening starting at 9pm.
  • Crews will be drilling sound wall foundation shafts and removing pieces of the existing roadway in preparation for retaining wall construction and repairs to the existing roadway.

  • Crews are starting to form up the cast in place sound walls on either side of the northbound bridge over Enfield Road.

  • Crews are constructing retaining walls and a piece of sound wall 16 along the shoulder of northbound MoPac between Enfield Road and Windsor Road. They are also installing roadway base material in preparation for asphalt paving in the area.
  • Crews are constructing retaining walls and a piece of sound wall 15 along the shoulder of northbound MoPac between Windsor and Westover. They are also installing roadway base material in preparation for asphalt paving in the area.
  • Crews have begun excavation activities for the shared use path that will run along the southbound MoPac frontage road. The area cuerrently being worked on is between Braker Lane and Capital of Texas Highway.
  • Questions?

    Call our 24 hour hotline 512-270-5000

  • Stay Updated

    Keep up to date on conversation, closures, and construction updates.

    Sign Up For Email or Text ยป

  • Twitter Update